Wow!! De-launching work of steel girders of Andheri Gokhale Bridge completed in record breaking time

by Ana Lopez

(from our representative)
Mumbai: De-launching work of all 16 steel girders of Gokhale Road Over Bridge at Andheri Station of Western Railway has been successfully completed in record breaking time in major block taken during night from March 11 to March 12, 2023.
According to the Railways, a four-and-a-half-hour block was taken on Up Slow and Up and Down Fast Lines, Platform No. 4 and an eight-hour block on Fifth Line and Platform No. 9, while a two-hour block was taken on Up and Down Harbor Line.
Two spans were dismantled east of Gokhale ROB in Andheri during the midnight block taken by the Railways on March 11 and 12, 2023. The abutment in the eastern direction will be dismantled and the eastern direction will now be handed over to the Mumbai Municipal Corporation. The work of dismantling and de-launching the ROB girder coming under the railway section has been completed.